Adjusted contract (ex-GST)

$2,100,000

+ GST $210,000 = $2,310,000 inc

Base contract
$2,100,000
Approved variations
$0
Pending variations
$214,000
Steel
180 t · 960 marks
Project manager
Marwan Haddad
Programme
08 Dec 2025 → 30 Sept 2026
Fabrication progress34%

Tekla model

No model imported yet — project in on hold.

Production

960 marks scheduled — fabrication not yet started.

Purchase orders (0)

No purchase orders raised.

Claims & variations

Claim 03 Apr 2026
$178,000 Draft
VO-2026-024 Shade canopy geometry change — architect RFI-212
$214,000 Submitted