Variation register · contract relations
Variations
Every design change and client-directed variation is raised here as a VO, priced, and tracked to approval.
Approved variations roll into the project's contract value and the next
progress claim automatically.
Approved variations
$411,400
Pending (submitted)
$452,500
Register entries
8
Raise a variation
| VO | Project | Description | Value | Marks | Status | Actions |
|---|---|---|---|---|---|---|
| VO-2026-041 | LE-2026-018 | Grid F truss upgrade 460UB→530UB (Rev C)Perth Airport T1 Domestic Expansion | $96,500 | 46 | Submitted | |
| VO-2026-038 | LE-2026-018 | Additional roof plant support steel — RTU-4Perth Airport T1 Domestic Expansion | $84,000 | 28 | Approved | |
| VO-2026-035 | LE-2026-018 | Revised connection detail — moment frame L2Perth Airport T1 Domestic Expansion | $130,000 | 62 | Approved | |
| VO-2026-030 | LE-2026-021 | Podium transfer beam — client-added mezzanineECU City Campus — Podium Steel | $142,000 | 88 | Submitted | |
| VO-2026-024 | LE-2025-041 | Shade canopy geometry change — architect RFI-212Optus Stadium — East Concourse Shade Structure | $214,000 | 120 | Submitted | |
| VO-2026-019 | LE-2026-014 | Stair balustrade — upgrade to 316 SS handrailMurdoch Health & Knowledge Precinct — Bldg B | $88,400 | 34 | Approved | |
| VO-2026-012 | LE-2025-047 | Canopy fascia extension — 6.2 mNV Apartments & Novotel — Balustrade & Canopy | $47,800 | 22 | Approved | |
| VO-2026-008 | LE-2026-009 | Additional galvanising — coastal exposure C5Curtin University — Exchange Precinct Bldg 5 | $61,200 | — | Approved |