Lighthouse Engineering

Purchase orders · steel · galvanising · coatings

Procurement

Value on order

$455k

ex-GST

Open POs

13

of 15

Overdue deliveries

2

chase suppliers

Suppliers

9

active this month

Request for quote · steel

Source the nested steel for Perth Airport T1 Domestic Expansion, quote-first, because the price moves.

ProfileGradeTonnesEst. rateEst. value
460UB82.1300PLUS28.4$1,560/t$44,304
310UC158300PLUS23.3$1,560/t$36,348
530UB92.4300PLUS18.3$1,560/t$28,548
PL20 Gr250AS/NZS 3678 Gr25016.9$1,750/t$29,575
610UB125300PLUS15.8$1,560/t$24,648
250UC89.5300PLUS9.7$1,560/t$15,132
360UB56.7300PLUS8.4$1,560/t$13,104
150x150x9 SHSC350L08.1$1,950/t$15,795
300PFC300PLUS5.0$1,650/t$8,250
200x100x6 RHSC350L02.5$1,950/t$4,875
PL16 Gr350AS/NZS 3678 Gr3501.5$1,750/t$2,625
Total137.9 t$223,204

Send to suppliers

Direct purchase order

Consumables straight from the library, or a generic milestone PO to a subcontractor. No quote needed.

PO total (ex-GST)

$210

Purchase order register

PO Supplier Project Items Value (ex-GST) Raised ETA Status
PO-2026-0408 Southern Steel Group LE-2026-018 380PFC ×12 $15,288 04 July 2026 11 July 2026 2 days late Overdue
PO-2026-0380 Ajax Fasteners LE-2026-014 M24 8.8/S HDG ×20 boxes $8,040 02 July 2026 10 July 2026 3 days late Overdue
PO-2026-0405 Kingfield Galvanizing LE-2026-018 HDG — 42 assemblies (18.4 t) $22,080 08 July 2026 16 July 2026 Sent
PO-2026-0385 BlueScope Distribution LE-2026-027 610UB125 ×18 $51,156 06 July 2026 28 July 2026 Sent
PO-2026-0412 InfraBuild Steel LE-2026-018 530UB92.4 ×20, 310UC158 ×14 $74,020 10 July 2026 21 July 2026 Confirmed
PO-2026-0398 Vulcan Steel LE-2026-023 150×150×9 SHS ×60, 200×100×6 RHS ×40 $51,760 27 June 2026 20 July 2026 Confirmed
PO-2026-0389 Complete Coatings WA LE-2026-009 Blast + IZS + 2-pack — 236 t package $61,400 18 June 2026 25 July 2026 Confirmed
PO-2026-0401 Midalia Steel LE-2026-014 360UB56.7 ×24, 250UC89.5 ×10 $36,958 30 June 2026 09 July 2026 Part-received
PO-2026-0901 InfraBuild Steel LE-2026-014 460UB82.1 ×5, 530UB92.4 ×17, 310UC158 ×7 $56,254 13 July 2026 Invalid Date Draft
PO-2026-0902 BlueScope Distribution LE-2026-014 610UB125 ×2 $5,684 13 July 2026 Invalid Date Draft
PO-2026-0903 Vulcan Steel LE-2026-014 150x150x9 SHS ×22, 200x100x6 RHS ×16 $19,496 13 July 2026 Invalid Date Draft
PO-2026-0904 Surdex Steel LE-2026-014 PL20 Gr250 ×10, PL25 Gr350 ×3, PL16 Gr350 ×14 $50,480 13 July 2026 Invalid Date Draft
PO-2026-0905 Southern Steel Group LE-2026-014 300PFC ×2 $1,972 13 July 2026 Invalid Date Draft
PO-2026-0394 Surdex Steel LE-2026-018 PL16 Gr350 ×10, PL20 Gr250 ×8 $32,260 24 June 2026 03 July 2026 Received
PO-2026-0377 Midalia Steel LE-2026-005 200UC59.5 ×16 $12,992 20 June 2026 27 June 2026 Received

Spend by supplier

Last 12 months vs the year before · $5.57M total

Negotiation leverage
Supplier Category Last 12 mo Prior 12 mo Change Share
InfraBuild Steel $2.14M $1.76M ▲ 22%
Midalia Steel Steel $1.39M $1.51M ▼ 8%
Vulcan Steel Steel $905k $640k ▲ 41%
Perth Galvanizing Galvanising $512k $470k ▲ 9%
Altex Coatings Surface treatment $318k $355k ▼ 10%
Ajax Fasteners Bolts & fixings $214k $168k ▲ 27%
BlastOne Abrasives Consumables $96k $88k ▲ 9%