Lighthouse Engineering

LE-2026-014 · Multiplex

Murdoch Health & Knowledge Precinct — Bldg B

← All projects
Fabrication Healthcare · Murdoch, WA

Adjusted contract (ex-GST)

$4,288,400

+ GST $428,840 = $4,717,240 inc

Base contract
$4,200,000
Approved variations
$88,400
Pending variations
$0
Steel
388 t · 1,980 marks
Project manager
Marwan Haddad
Programme
19 Jan 2026 → 04 Sept 2026
Fabrication progress71%

Tekla model

FilePerthAirportT1_RevD.bswx
Revision Confirmed Rev D
Assemblies / parts22 / 428
Imported13 July 2026
Open Model Import →

Production

1,980 marks scheduled, fabrication not yet started.

Purchase orders (7)

PO-2026-0401 Midalia Steel
$36,958 Part-received
PO-2026-0380 Ajax Fasteners
$8,040 Overdue
PO-2026-0901 InfraBuild Steel
$56,254 Draft
PO-2026-0902 BlueScope Distribution
$5,684 Draft
PO-2026-0903 Vulcan Steel
$19,496 Draft
PO-2026-0904 Surdex Steel
$50,480 Draft
PO-2026-0905 Southern Steel Group
$1,972 Draft

Claims & variations

Claim 06 Jun 2026
$388,000 Certified
Claim 05 May 2026
$355,000 Paid
VO-2026-019 Stair balustrade — upgrade to 316 SS handrail
$88,400 Approved

Recent activity

  • Meeting
    Monthly progress & claim review Marwan Haddad · Multiplex
    03 July 2026