Lighthouse Engineering

LE-2026-018 · CPB Contractors

Perth Airport T1 Domestic Expansion

← All projects
Fabrication Aviation · Perth Airport, WA

Adjusted contract (ex-GST)

$7,064,000

+ GST $706,400 = $7,770,400 inc

Base contract
$6,850,000
Approved variations
$214,000
Pending variations
$96,500
Steel
612 t · 3,140 marks
Project manager
Marwan Haddad
Programme
16 Feb 2026 → 27 Nov 2026
Fabrication progress58%

Tekla model

FilePerthAirport-T1_RevC.bswx
Revision Submitted Rev C
Assemblies / parts986 / 3,140
Imported09 July 2026
Open Model Import →

Production

Nested
2
Cutting
2
Drilling
2
Fit-up
2
Welding
3
QA / NDT
2
Surface Treatment
3
Dispatch
2
Complete
4
Open shop-floor board →

Purchase orders (4)

PO-2026-0412 InfraBuild Steel
$74,020 Confirmed
PO-2026-0408 Southern Steel Group
$15,288 Overdue
PO-2026-0405 Kingfield Galvanizing
$22,080 Sent
PO-2026-0394 Surdex Steel
$32,260 Received

Claims & variations

Claim 07 Jun 2026
$742,000 Certified
Claim 08 Jul 2026
$610,500 Submitted
VO-2026-041 Grid F truss upgrade 460UB→530UB (Rev C)
$96,500 Submitted
VO-2026-038 Additional roof plant support steel — RTU-4
$84,000 Approved
VO-2026-035 Revised connection detail — moment frame L2
$130,000 Approved