Lighthouse Engineering

LE-2026-021 · Multiplex

ECU City Campus — Podium Steel

← All projects
Detailing Education · Perth CBD, WA

Adjusted contract (ex-GST)

$8,900,000

+ GST $890,000 = $9,790,000 inc

Base contract
$8,900,000
Approved variations
$0
Pending variations
$142,000
Steel
740 t · 4,020 marks
Project manager
Grace Whitlam
Programme
04 May 2026 → 19 Mar 2027
Fabrication progress22%

Tekla model

FileECUCity-Podium_RevA.bswx
Revision Confirmed Rev A
Assemblies / parts1,210 / 4,020
Imported02 July 2026
Open Model Import →

Production

4,020 marks scheduled — fabrication not yet started.

Purchase orders (0)

No purchase orders raised.

Claims & variations

VO-2026-030 Podium transfer beam — client-added mezzanine
$142,000 Submitted