LE-2026-023 · Georgiou
Westport Logistics Hub — Stage 1 Portal Frames
Procurement Infrastructure · Kwinana, WA
Adjusted contract (ex-GST)
$3,400,000
+ GST $340,000 = $3,740,000 inc
- Base contract
- $3,400,000
- Approved variations
- $0
- Pending variations
- $0
- Steel
- 410 t · 890 marks
- Project manager
- Grace Whitlam
- Programme
- 01 June 2026 → 29 Jan 2027
Fabrication progress15%
Tekla model
No model imported yet — project in procurement.
Production
890 marks scheduled — fabrication not yet started.
Purchase orders (1)
PO-2026-0398 Vulcan Steel
$51,760 Confirmed