Lighthouse Engineering

LE-2026-027 · Acciona

Gudai-Darri — Conveyor Support Steel

← All projects
Detailing Resources · Pilbara, WA

Adjusted contract (ex-GST)

$5,600,000

+ GST $560,000 = $6,160,000 inc

Base contract
$5,600,000
Approved variations
$0
Pending variations
$0
Steel
520 t · 2,240 marks
Project manager
Grace Whitlam
Programme
22 June 2026 → 14 May 2027
Fabrication progress8%

Tekla model

FileGudaiDarri-Conveyor_RevA.bswx
Revision Confirmed Rev A
Assemblies / parts688 / 2,240
Imported06 July 2026
Open Model Import →

Production

2,240 marks scheduled — fabrication not yet started.

Purchase orders (1)

PO-2026-0385 BlueScope Distribution
$51,156 Sent

Claims & variations